Boeing cuts about 2,500 jobs from its airplane division as the 737 ramp slips into 2027

News story

Boeing will reduce the workforce of its Commercial Airplanes division by about 5 percent through attrition and involuntary layoffs, the division's chief, Stephanie Pope, told employees in a memo on Monday, Reuters reported. The division employed 50,494 people at the end of 2025, so the cut reaches roughly 2,500 jobs, with notices expected to begin in December. Boeing is slowing its planned production increases, and a significant ramp of 737 Max output is now not expected until the second half of 2027.

Boeing cuts about 2,500 jobs from its airplane division as the 737 ramp slips into 2027

Boeing has a record order book and is cutting jobs anyway, because the order book is not the problem. The division chief of Boeing Commercial Airplanes, Stephanie Pope, told employees in an internal memo on Monday that the division will reduce its staffing by about 5 percent over the coming months, through a combination of attrition and involuntary layoffs, Reuters reported. The commercial division employed 50,494 people at the end of December 2025, so a 5 percent reduction reaches about 2,500 jobs. Affected employees will begin receiving notices in December at the earliest. Boeing is required in many states to give workers 60 days of notice.

The reason is the production ramp that will not come on schedule. Boeing told investors in its third quarter results on October 27 that raising output has taken longer than expected as the company gives its factories and suppliers more time to stabilise, and Pope's memo says the revised schedules and lower aircraft output have left the division overstaffed against its updated business plan. Chief executive Kelly Ortberg told analysts last month that Boeing would miss its 737 production and delivery targets for this year. The company is working to hold a rate of 47 Max jets a month, a level now expected in early 2027 rather than the summer of 2026, and does not expect to reach 52 a month until the second half of 2027. The widebody 787 line is also moving slowly from 8 jets a month toward 10.

The money shows the strain. The commercial unit took in roughly 10.7 billion dollars of revenue in the third quarter and posted an operating loss of 697 million dollars. Against that sits a backlog of more than 6,300 airplanes valued at a record 612 billion dollars: years of sold work that the factories cannot yet build at the planned pace. The memo spared some sites. Employees in Wichita, Kansas, and Tulsa, Oklahoma were told in a separate message that they are not being considered for layoffs, voluntary separation or early retirement, KMUW reported. The International Association of Machinists District 751, which represents much of the Seattle area workforce, told Axios it had been notified of the plan. How the 2,500 jobs divide between layoffs and unfilled departures has not been announced.